Archived - Status report on projects operating with specific Treasury Board approval

Archived information

This Web page has been archived on the Web. Archived information is provided for reference, research or record keeping purposes. It is not subject to the Government of Canada Web Standards and has not been altered or updated since it was archived. Please contact us to request a format other than those available.

Project name and project phase Original estimated total cost (dollars) Revised estimated total cost (dollars) Actual total cost (dollars) 2016–2017 Main Estimates (dollars) 2016–2017 Planned spending (dollars) 2016–2017 Total authorities (dollars)a 2016–2017 Actual spending (dollars) Expected date of close-out
Link to INAC's Program Alignment Architecture: The North — Program 4.3: Northern Land, Resources and Environmental Managementb
FOX-E — Durban Island Minesc 1,179,305,914 1,227,687,834 12,065,436 0 0 165,600 0 2015–2016
Tundra Mine 21,865,807 0 10,359,160 7,577,035 13,338,419 2018–2019
Bullmoose and Ruth Mines 11,156,542 0 4,243,409 8,503,361 6,654,108 2022–2023
United Keno Hills Mines 52,344,484 0 5,468,639 8,260,680 3,465,159 2023–2024
Great Bear Lake Mines 24,241,297 0 2,967,995 7,552,728 3,007,701 2026–2027
Giant Mine 374,549,096 0 54,330,385 41,673,921 38,827,768 2028–2029
Link to INAC’s Program Alignment Architecture: The North — Program 4.2: Northern Science and Technology
Canadian High Arctic Research Stationd 145,524,772 195,537,456 141,998,483 42,710,236 43,784,639 55,976,262 46,877,530 2018–2019
a In this table, the column "Total Authorities" reflects only the annual planned spending for fiscal year 2016–2017 as outlined in the original estimated total cost or revised estimated total cost columns.
b In 2016–2017 funding for Northern Contaminated Sites Program under Northern Land, Resources and Environmental was made available through the Supplementary Estimates A process. Planned spending amounts were determined from the approved detailed work plans.
c FOX-E fully completed all remediation activities in 2015–2016 and is in the process of being closed. There were no expenditures incurred or planned costs in 2016–2017 and no additional costs are expected for this site in the future.
d The project scope was re-defined and the total project cost was amended to $145.5 million in May 2014, with an increase of $50 million in 2015. Actuals are lower than Authorities as some activities (~$9 million) have been postponed from 2016–2017 to 2017–2018.

Note that 2016–2017 planned spending corresponds to 4.2.2 (Science initiatives) and includes administration cost to support the Northern Science and Technology program.

Please note that the original estimated total cost and revised estimated cost total includes employees’ benefit plans and accommodation.

Did you find what you were looking for?

What was wrong?

You will not receive a reply. Don't include personal information (telephone, email, SIN, financial, medical, or work details).
Maximum 300 characters

Thank you for your feedback

Date modified: